Agrivoltaics (Agri-PV): frequently asked questions and answers
1. Definition & technology · 2. Economics & remuneration · 3. Planning law & privileged status · 4. Planning & permitting
1. Definition & technology
What is agrivoltaics (Agri-PV)?
Agrivoltaics (agri-photovoltaics, Agri-PV) means the simultaneous agricultural and energy use of the same land. In Germany it is clearly defined in the standard DIN SPEC 91434.
According to DIN SPEC 91434, section 3, an agrivoltaic system is the combined use of land in which:
- agricultural production is the primary use, and
- electricity generation by photovoltaics is the secondary use.
Agrivoltaics is therefore not a conventional ground-mounted solar system but an integrated land-use concept in which farming remains functionally, economically and structurally at the centre.
Core principles of agrivoltaics under DIN SPEC 91434
- Primacy of agriculture: farming leads the planning, design and operation of the system.
- Land efficiency: the same land is used twice, for food production and renewable energy.
- System integration: PV systems are designed so that cultivation, harvesting, irrigation and soil management remain possible.
- Regulatory distinction: agrivoltaics is legally and technically defined separately from conventional ground-mounted PV.
Strategic importance of agrivoltaics
Agrivoltaics stabilises farm incomes, increases land productivity per hectare and creates a systemic link between the energy and agricultural sectors. At the same time it contributes directly to the regional energy transition without displacing farmland.
Why is agrivoltaics discussed as a compromise?
Ground-mounted solar farms often create a conflict between food and power production. In Rhineland-Palatinate, for example, conventional solar farms are to be built mainly on low-yield sites (soil quality index below 35). Agrivoltaics offers a compromise because it combines land uses rather than restricting them.
What are the benefits of agrivoltaics for agriculture?
Besides dual land use, a well-designed agrivoltaic system offers:
- Less soil erosion and evaporation.
- Better control of irrigation.
- Protection against extreme weather such as heavy rain, hail and excessive solar radiation (especially with horizontal mounting).
- Potentially higher resilience and agricultural yields.
Which technical solutions exist?
There are two main types:
- Vertical systems: modules are installed vertically, often bifacial, so that the land between the rows remains usable.
- Horizontal systems: modules are elevated (e.g. in fruit growing) so that work can continue underneath them.
2. Economics & remuneration
How do costs and yields compare with ground-mounted solar?
Because of its more complex construction, agrivoltaics is more expensive than conventional ground-mounted solar, which under the EEG 2027 is only partly offset by a bonus of 0.5 ct/kWh. Ylektra’s tracking technology is an exception: turnkey costs are higher than for ground-mounted solar, but they are more than compensated by significantly higher yields. See our comparison agrivoltaics vs conventional solar farms.
What are the levelised costs of electricity?
With levelised costs of electricity of 5 to 10 ct/kWh, agrivoltaics is already competitive with other renewable energy sources.
What remuneration do agrivoltaic systems receive under the EEG 2027?
In short: Under the government bill for the EEG 2027 (cabinet decision of 29 July 2026), agrivoltaic systems receive an elevation bonus of 0.5 ct/kWh – the same amount for Category I and Category II under DIN SPEC 91434. There is no longer a dedicated tender segment for agrivoltaics.
- Systems up to 1 MW (no tender required): statutory value of 6.2 ct/kWh + 0.5 ct/kWh bonus = 6.7 ct/kWh (§ 48 (1) in conjunction with (1b) EEG 2027).
- Systems above 1 MW (tender required): awarded value up to the ceiling of 5.9 ct/kWh (§ 37b) + 0.5 ct/kWh bonus = maximum 6.4 ct/kWh (§ 38a EEG 2027).
- The former agrivoltaics sub-segment (§ 37d EEG 2023) is abolished. Agrivoltaics competes with standard ground-mounted solar in the common first segment, with an annual tender volume of 14,000 MW.
- Support is paid through two-way contracts for difference (CfDs): if the technology-specific annual market value exceeds the statutory value, systems of 100 kW and above pay a refinancing contribution (§ 21d, § 3 no. 34 EEG 2027).
Status: 14 October 2026. The EEG 2027 is scheduled to enter into force on 1 January 2027 but has not yet been adopted; the Bundestag is debating the bill (hearing on 5 October 2026). Follow the latest developments in our continuously updated article EEG 2027 and agrivoltaics: current status; see also our detailed analysis of the cabinet decision and grid connection package.
Which remuneration rules apply until the EEG 2027 enters into force?
The EEG 2023 applies until 31 December 2026. The technology bonus of 2.5 ct/kWh for agrivoltaics (“special solar installations”) introduced with Solar Package I is subject to EU state aid approval. Without that approval:
- The maximum bid size in tenders is 20 MW per installation.
- Special solar installations such as elevated agrivoltaics receive a bonus of 0.5 ct/kWh on top of the awarded value (e.g. 5 ct bid + 0.5 ct bonus).
- The ceiling price of 9.5 ct/kWh from Solar Package I does not apply.
The state aid approval of the EEG 2023 expires on 31 December 2026.
Which requirements apply for the agrivoltaics bonus?
Only systems that qualify as a special solar installation under § 37 (1) no. 3 EEG and are built in accordance with DIN SPEC 91434 (or DIN SPEC 91492 for livestock farming) receive the bonus:
- Category I: elevated systems with horizontally oriented modules and a clearance of at least 2.10 m.
- Category II: ground-level systems with a clearance of at least 0.80 m – only with exclusively vertical orientation or tracker systems.
- Annual proof of agricultural use: if it is missing, the statutory value is reduced by 0.5 ct/kWh (§ 48 (5) or § 54 (2) EEG 2027). The reduction is reversed retroactively if the proof is submitted in the following year.
Which deadlines apply after an agrivoltaics tender award?
Under the EEG 2027, an awarded system must go at least partly into operation within 24 months, otherwise the award lapses (§ 37e).
- Commissioning more than 18 months after publication of the award reduces the statutory value by 0.3 ct/kWh (§ 54 (1) EEG 2027).
- The payment authorisation procedure (§ 38a EEG 2023) with its 26-month deadline is abolished.
- The requirement that bidder and operator be identical is dropped: agrivoltaics awards can be transferred after the award – easing turnkey projects and the entry of institutional investors.
- Bids are tied to the named land parcel, but agrivoltaic awards may be used flexibly across the agrivoltaic and peatland-PV sites named in the bid (§ 38 (1) no. 1 ©).
What does the grid connection package mean for agrivoltaic projects?
The grid connection package (cabinet decision of 29 July 2026) introduces location-based steering in grid congestion hot spots and speeds up grid connections:
- In regions that foreseeably cannot absorb additional wind or solar feed-in, compensation for curtailment is dropped – capped at 20 % of annual generation (18 % in wind priority areas) and limited to 6 years.
- Grid capacity will be assessed on typical feed-in profiles rather than peak feed-in.
- Grid operators may prioritise connection requests and reserve capacity.
In practice: grid compatibility should be assessed before securing land and submitting a bid. Ylektra already includes the grid situation in its site analysis. The details of the grid connection package are based on the federal government’s press release.
Do agrivoltaic systems have to meet the ecological minimum criteria?
No. Under § 38 (1) no. 4 EEG 2027, the ecological minimum criteria (§ 37 (1a)) apply only to standard ground-mounted sites under § 37 (1) no. 1 or 2. Agrivoltaics is exempt – agricultural dual use counts as a sufficient ecological justification in its own right.
3. Planning law & privileged status
When is an agrivoltaic system privileged under § 35 (1) no. 9 of the German Building Code (BauGB)?
Since December 2023, agrivoltaic systems in the outer zone (Außenbereich) have been privileged under strict conditions:
- The land must be arable land or grassland (as defined in the EEG).
- There must be a spatial and functional connection to an agricultural or forestry business.
- The footprint must not exceed 25,000 m² (2.5 ha).
- Only one system may be operated per farmstead or business location.
- After use ends, dismantling including unsealing is mandatory.
Our guide Agrivoltaics permitting under Section 35 BauGB explains the details.
What does “spatial and functional connection” mean?
The spatial connection must exist to the main buildings of the farm. A functional connection is recognised where there are synergies, e.g. protection against erosion, frost or hail provided by the modules.
Are there privileges along transport routes (§ 35 (1) no. 8 BauGB)?
Yes. Agrivoltaics can be privileged along motorways or railway lines (at least two main tracks). The distance must not exceed 200 metres from the edge of the carriageway, and glare must be ruled out.
What applies to systems that are not privileged?
If the system does not qualify (e.g. larger than 2.5 ha or no link to a farm), the municipality must create planning law. This is usually done with a project-related development plan (§ 12 BauGB), which can designate uses such as a “special area for agrivoltaics”.
How do spatial planning objectives affect agrivoltaics?
PV systems are often excluded in priority areas (e.g. for agriculture). For agrivoltaics, however, a target deviation procedure (§ 6 of the Federal Spatial Planning Act, ROG) can be promising, because agricultural use is maintained and renewable energy is in the “overriding public interest” (§ 2 EEG).
4. Planning & permitting
Is a building permit required?
Yes, agrivoltaics almost always requires a building permit, usually under the simplified procedure of the respective state building code (e.g. § 66 LBauO in Rhineland-Palatinate). Systems are exempt only if a development plan already contains exact provisions on location, size etc., which is rare in practice.
What must the agricultural use concept contain?
For a system to be recognised as agrivoltaics, a use concept must be submitted (under DIN SPEC 91434, or DIN SPEC 91492 for livestock). It must show, for example, that the agricultural yield is at most one third below the reference yield and that agricultural use predominates. The concept is usually agreed with the regional chamber of agriculture.
What are the nature conservation requirements?
Construction is an intervention in nature and landscape (§ 14 of the Federal Nature Conservation Act, BNatSchG). A nature conservation report must be prepared, and unavoidable impacts must be offset (compensation measures). Even for privileged projects, a security deposit for dismantling and compensation is customary.
Is an environmental impact assessment (EIA) required?
As a rule, agrivoltaic systems are not subject to a mandatory EIA. A preliminary EIA screening may be required only in exceptional cases for very large systems if significant adverse environmental effects are expected. A permit under immission control law is not required either. A species protection assessment is, however, mandatory.
Which operator models exist?
There are three common models:
- The farmer builds and operates the system.
- Ylektra leases private farmland, builds the system and the farmer continues to cultivate the land.
- A municipality leases its own farmland to Ylektra and the farmer continues to cultivate the land.
Landowners will find more answers in our land lease FAQ.
Which certifications are required?
Depending on site, system type and permitting route, agrivoltaic projects require various certifications and evidence on four levels:
1. Technical certifications
- Module, inverter and system certificates according to applicable IEC/EN standards
- Structural verification of the mounting system (DIN/EN standards, wind and snow load zones)
- Electrical and safety certificates according to VDE regulations
- Grid connection and protection concepts including technical approvals
2. Construction and permitting documents
- Building application documents including site plans, access and structural analysis
- Environmental, nature and species protection reports (depending on site)
- Fire protection and safety concepts (where required)
3. EEG and privileged-status evidence
- Proof of privileged status under building and planning law
- EEG compliance documentation
- Documentation for remuneration models and eligibility
4. Certification of the agricultural use concept (DIN SPEC 91434)
- Certification of the agrivoltaic operating concept under DIN SPEC 91434 to formally recognise agriculture as the primary use
- Proof of permanent agricultural use in line with the technical system layout
- Compliance with the agricultural requirements for agrivoltaic systems
Recurring evidence:
- annual evidence (operations, use, cultivation)
- or every three years (structured re-certification / review according to the certification scheme)
Ylektra’s role: Ylektra coordinates and carries out all certification and evidence processes – including the DIN SPEC certification of the agricultural concept and the ongoing annual or three-yearly evidence. This secures regulatory compliance over the long term and systematically reduces project risk for operators, investors and landowners.
How long does it take from project development to construction?
Project duration is driven primarily by permitting and depends on the legal classification (privileged vs. not privileged) and site complexity. Based on real project development processes, the following time frames apply:
Privileged agrivoltaic projects
➡️ approx. 8 to 14 months from project development to start of construction
Drivers:
- simplified permitting processes
- structured documentation
- faster coordination with authorities
- standardised project architecture
Non-privileged agrivoltaic projects
➡️ approx. 16 to 24 months from project development to start of construction
Drivers:
- extended permitting and review procedures
- additional environmental and planning processes
- greater procedural complexity
- longer coordination loops with authorities