What we do
Project development, EPC and storage for agrivoltaics
In short
Ylektra develops agrivoltaic projects with battery storage across Germany: from securing land with farmers and municipalities through planning, permitting and grid connection to ready-to-build status. We then build the plants ourselves as EPC contractor.
As of October 2026 · Editor: Ylektra GmbH
- > 850 MWagrivoltaic and hybrid project pipeline
- > 950 haagricultural land in the pipeline
- 8–14 monthsto construction start for privileged projects
- 16–24 monthswith a development plan (not privileged)
01 · Develop
Five steps to a ready-to-build project
One point of contact from the first conversation on the farm to the grid connection.
- 1
Site and land
GIS analyses of irradiation, grid proximity, regional planning and protected areas. The grid situation is part of the site analysis from the start. We then secure the land together with owners and farmers. - 2
Planning and layout
Row spacing, height and orientation follow the working width and crop rotation of the farm. In Armsheim, 13.5 m row spacing leaves a 12 m working width for standard farm machinery. - 3
Permitting
Building application for privileged systems (Section 35 of the Federal Building Code) or a development plan with the municipality, plus nature conservation report, species protection assessment and an agricultural use concept under DIN SPEC 91434. - 4
Grid connection
Connection request, coordination with the grid operator and, where possible, a shared connection for solar and storage, which lowers cost and waiting time. - 5
Financing and ready-to-build
Revenue model (EEG, PPA or direct marketing), financing and certification. Once the project is ready to build, our EPC team takes over.
02 · Build
Turnkey EPC and operation
EPC stands for engineering, procurement and construction: planning, procurement and construction from one source, to a fixed scope of work.
Engineering
Detailed design of tracker field, electrical system and storage, structural design for the wind and snow load zone, layout based on the working width and crops of the farm.
Procurement
Modules, trackers, inverters and storage certified to applicable IEC/EN standards, with quality assurance so that equipment and design meet the project targets.
Construction
Pile driving, mounting and electrical installation with licensed construction partners. Site management, grid connection, commissioning and acceptance remain with Ylektra.
On request we also take over operation and asset management over the 30-year life: monitoring, maintenance, marketing, the annual proof of agricultural use under DIN SPEC 91434 and decommissioning, secured by a decommissioning bond.
03 · Technology
Trackers, storage and energy management
Single-axis trackers
Module rows follow the sun from east to west and generate more electricity per hectare than fixed systems. For field work they turn into a convenient position. Row spacing is usually 14 m on arable land and from 7 m on grassland; pile-driven posts keep sealing below 1 %.
Battery storage at the same connection
The battery absorbs solar power when the grid is full or prices are negative and releases it when it is needed. Two to four hours of storage, depending on the project.
Energy management and revenue stacking
An energy management system decides when to feed in, store or trade: EEG or PPA, day-ahead and intraday trading, and grid services such as balancing energy.
References
Projects in development and construction
Armsheim · Rhineland-Palatinate
About 50 MW on about 70 ha
Single-axis trackers, a large-scale battery with two to four hours of storage, around 90 % of the land stays arable. Urban development contract approved on 10 June 2026.
Project reportSoest-Deiringsen · North Rhine-Westphalia
About 5.1 MWp, under construction
Developed and built by Ylektra as EPC general contractor. Trackers in 2P configuration, grid connection shared with a wind farm, commissioning planned for mid-2027.
Project reportFor investors & partners
Partner with Ylektra
Acquire ready-to-build projects, co-develop from an early stage or co-invest in storage. Landowners in Germany find our lease offer on the German site.
FAQ
Questions on development, EPC and technology
As of October 2026
How long does it take to develop an agrivoltaic project in Germany?
For privileged agrivoltaic systems under Section 35(1) no. 9 of the Federal Building Code, Ylektra expects about 8 to 14 months from project design to construction start. If the project needs a development plan, it takes about 16 to 24 months, because additional environmental and planning procedures are required.
What does EPC mean for an agrivoltaic system?
EPC stands for engineering, procurement and construction. The EPC general contractor takes on planning, procurement and construction of a plant from one source, up to turnkey commissioning. In its agrivoltaic projects, Ylektra is project developer and EPC general contractor at the same time.
What is an agrivoltaic system with trackers?
In an agrivoltaic system with single-axis trackers, the module rows turn with the sun over the course of the day. Arable farming continues between the rows, and the modules can be moved into a convenient position for field work. Under DIN SPEC 91434, such systems belong to category II.
What does revenue stacking mean?
Revenue stacking means that a plant uses several revenue sources at the same time: support under the EEG or a PPA, wholesale trading on the day-ahead and intraday markets, and grid services such as balancing energy or congestion management. An energy management system decides which source is used when.
How much land is sealed by an agrivoltaic system with trackers?
Very little, because the trackers stand on pile-driven posts. In the Soest project, sealing is below 1 % of the area, and more than 90 % remains available for farming.