In short: yes. Agrivoltaics in the privileged segment can still pay off under the EEG 2027 if the realisation is right. With state-of-the-art tracker technology and cost-efficient, leanly organised project realisation, Ylektra enables project returns (IRR) of more than 8 %. For bank-financed, i.e. debt-leveraged, projects, equity returns of more than 20 % are possible. If a large-scale battery is also integrated, both to protect against negative-price hours and to optimise the marketing of the solar power generated, the net present value rises significantly again. With the cabinet decision of 29 July 2026 on the EEG 2027, which has been before the Bundestag since September 2026, the regulatory basis is changing fundamentally at the same time.
Is it worth it? The key figures at a glance
Even after the agrivoltaics bonus was cut from 2.5 ct/kWh to 0.5 ct/kWh, agrivoltaics in the privileged segment remains an attractive asset class, provided the realisation is cost-efficient:
- Project return (IRR): more than 8 % is achievable for carefully calculated, turnkey agrivoltaic projects in the first segment.
- Return on equity: more than 20 % for bank-financed, i.e. debt-leveraged, projects; leverage through low-cost debt is the decisive return driver.
- With large-scale storage on top: if a large-scale battery is added that both protects against negative-price hours and optimises the marketing of the solar power (feeding in specifically during high-price phases instead of the price troughs), the project’s net present value (NPV) rises significantly again. The battery is therefore not a cost block but an additional return lever.
These orders of magnitude appear consistently in current Ylektra project calculations for the first segment. Decisive for achieving these values is efficient, cost-effective implementation, from EPC procurement and grid connection to the financing structure.
The EEG 2027 cabinet decision in figures
The government bill resets the economic parameters for ground-mounted solar and agrivoltaics:
- Applicable value (Section 48(1) of the EEG 2027 draft): 6.2 ct/kWh
- Maximum value in the first segment (Section 37b): 5.9 ct/kWh
- Annual tender volume: 14,000 MW
- Section 37d EEG 2023 (the previous agrivoltaics tender segment) is abolished without replacement; agrivoltaics will in future compete in the regular first segment
- In return, Section 38a(1) (systems > 1 MW) and Section 48(1b) (≤ 1 MW) secure a uniform bonus of 0.5 ct/kWh, equally for elevated (category I) and tracked (category II) systems. This raises the applicable value for an agrivoltaic system to 6.7 ct/kWh.
Because the state aid approval is expiring, the law must be in place in 2026; the Bundestag deliberations are therefore under time pressure.
Large-scale storage as an additional NPV lever
A common misunderstanding: a large-scale battery (BESS) is not primarily built to consume electricity locally, as such high consumption is not (yet) the rule on farms. With the increasing electrification of agriculture, this may of course change in future. Its economic contribution today arises at the following levels:
- Protection against zero and negative prices: instead of curtailing at negative exchange prices, generation is stored temporarily and marketed later.
- Marketing optimisation: the battery shifts solar power specifically from low-price midday hours into high-price time windows, with day-ahead and intraday trading instead of fixed feed-in at the average price.
- Ancillary services: in addition, balancing energy (aFRR/FCR) for the transmission system operators, where the grid allows it.
- Grid relief: a smoothed feed-in curve at the shared grid connection point, an argument against curtailment under the new location-based steering.
Taken together, these effects raise the net present value of an agrivoltaic project noticeably above the level of a pure ground-mounted system without storage. The exact uplift depends on battery size, layout and market environment and is calculated for each project.
Dual use at a shared grid connection
For farmers, the cabinet decision does not change the planning law privilege under Section 35 of the Federal Building Code (BauGB); actual cultivation of the land remains a central requirement for categorisation under DIN SPEC 91434. If agrivoltaics is combined with a large-scale battery at the same grid connection point, the farmer secures either capital income from marketing the electricity, if investing themselves, or a long-term, index-linked lease if Ylektra invests in the system.
Conclusion: yes, it pays off, with efficient realisation
The EEG 2027 marks the final transition from pure feed-in remuneration to market integration with the help of battery storage. Agrivoltaics in the privileged segment remains economically attractive: project returns above 8 % and, with a sensible debt structure, equity returns above 20 % are achievable if realisation is cost-efficient. An integrated large-scale battery raises the net present value significantly again, through protection against negative prices as well as optimised marketing. Ylektra structures and realises such projects along these new rules, from site assessment in the hot-spot context and battery sizing to the financing structure.
FAQ
Is agrivoltaics in the privileged segment still worthwhile under the EEG 2027?
Yes. With state-of-the-art tracker and battery technology and cost-efficient, turnkey realisation, project returns (IRR) of more than 8 % are achievable. For bank-financed projects, the return on equity rises to more than 20 % thanks to debt leverage.
Does an additional large-scale battery pay off economically?
Yes. A large-scale battery protects against negative-price hours and optimises the marketing of solar power by shifting feed-in specifically into high-price time windows. Together, both raise the net present value (NPV) of an agrivoltaic project significantly again.
Does the EEG 2027 cabinet decision change the planning law privilege for agrivoltaics?
No. The privilege under Section 35 BauGB remains. What is being tightened is the control of actual agricultural cultivation, to which the new 0.5 ct/kWh bonus is linked.
Why is the previous agrivoltaics tender segment being abolished?
The legislator repeals Section 37d EEG 2023 without replacement and transfers agrivoltaics into the regular first segment. This is compensated by the new bonus under Section 38a(1) and Section 48(1b) of the EEG 2027 draft.
What does the new location-based steering mean for projects in grid congestion regions?
In grid hot spots, curtailment without compensation will be possible in future, capped at 20 % (18 % in wind priority areas) of annual generation and limited to six years. Since bids are tied to the land parcel, grid compatibility becomes a preliminary check before the tender.
What happens next with the EEG 2027?
Following the cabinet decision of 29 July 2026, the Bundestag has been deliberating on the bill since September 2026. Because the state aid approval is expiring, the law is to be adopted in 2026.