At the end of June 2026, the Bundestag adopted the Infrastructure Future Act (Infrastruktur-Zukunftsgesetz) in order to noticeably accelerate planning and approval procedures for transport infrastructure projects. A change to the Federal Nature Conservation Act that looks inconspicuous at first glance is also of considerable relevance for the solar and storage industry. It is therefore directly significant for agrivoltaic projects such as those that Ylektra develops, builds and operates in Germany.
The core point: compensation payments and on-site compensation will rank equally
Until now, a clear order of priority applied to nature conservation compensation for unavoidable impacts on nature and the landscape: first it had to be examined whether an impact could be offset by compensation or replacement measures on site or in the surrounding area. Only if this was demonstrably impossible could a compensation payment to the competent nature conservation authority be considered. In addition, there was an extensive duty to justify this, and often a months-long search for suitable compensation land.
The Infrastructure Future Act now removes this order of priority: under the new Section 15(6a) of the Federal Nature Conservation Act (BNatSchG), compensation, replacement and compensation payments will in future rank equally. A justification of why direct compensation in nature is not possible is therefore no longer required. In this case, the search for compensation land can be dropped entirely. Instead, a payment is made to the Federal Environment Ministry or the competent state ministries, which is invested in nature conservation measures for that specific purpose.
Why does this also affect agrivoltaic systems and storage?
The new rule was originally aimed at classic transport infrastructure, military projects, telecommunications and projects financed from the special fund for infrastructure and climate neutrality. However, the recommendation of the lead Transport Committee extended its scope. Section 15(6a) sentence 3 BNatSchG now expressly provides that energy infrastructure falling under the overriding public interest under Section 2 EEG is also covered. The new rule therefore also applies to ground-mounted solar systems, including agrivoltaics. In addition, the scope was extended to storage under Section 11c of the Energy Industry Act (EnWG).
Distinction from the parallel amendment of the Federal Building Code
A similar rule is also planned in the ongoing amendment of the Federal Building Code (BauGB), but there only for projects realised through a development plan. The amendment to the Federal Nature Conservation Act now adopted in the Infrastructure Future Act goes much further. It expressly also covers installations privileged under building law, for example ground-mounted solar projects realised without their own development plan through a privilege under Section 35 BauGB. For the solar industry, the BNatSchG rule is therefore potentially the more widely effective of the two legislative changes.
Timetable and reactions from industry and nature conservation
The law requires the consent of the Bundesrat, which still has to approve it on 10 July 2026 before it can enter into force. The German Solar Industry Association (BSW-Solar) has long campaigned for exactly this simplification of nature conservation compensation for solar projects. It is therefore likely to welcome the extension to Section 2 EEG.
The transport sector also approves: infrastructure operators such as Deutsche Bahn expect equal treatment to bring a noticeable acceleration at the start of projects, because the search for land for compensation measures has so far taken a great deal of time. Nature conservation associations, on the other hand, view the change critically. They warn of a break with a principle of environmental and nature conservation law that has been established for around 50 years. They also fear a de facto weakening of on-site compensation. This criticism mainly concerns classic transport projects. Nevertheless, it is likely to continue to be discussed in its application to energy infrastructure.
What this means in practice for agrivoltaic projects
- Shorter approval procedures: The often months-long search for suitable compensation land can be dropped if a compensation payment is made instead.
- Less justification effort: Developers no longer have to prove in each individual case why on-site compensation is not possible.
- Greater planning certainty: A compensation payment can be calculated financially and scheduled, unlike an uncertain, often lengthy search for land that can delay the project timetable.
- No compromise on nature conservation quality: Compensation payments flow, earmarked, into nature conservation measures of the competent ministries and replace ecological compensation not in substance but in organisation.
For Ylektra as a project developer, EPC company and operator that actively manages approval procedures for tracker agrivoltaic systems, the new rule opens up an additional option in project planning, provided the Bundesrat approves as expected. Especially at sites with a limited supply of suitable compensation land in the surrounding area, this can make the difference between a project that is approved quickly and one that is blocked for months.
Conclusion
With the Infrastructure Future Act, a rule originally intended for transport, military and telecommunications projects is also opened up to solar installations and storage under the EEG and EnWG. Whether and to what extent this actually speeds up approval practice for agrivoltaic projects will become clear once the Bundesrat has approved it on 10 July and the first authorities apply the new equal ranking of compensation, replacement and compensation payments in practice. Ylektra is following further developments and will assess the impact on ongoing and planned projects here.